CITY OF DOWNEY CAPITAL IMPROVEMENT PROJECTS
CIP CATEGORY
of 2
/Page
PROJECT
LOCATION MAP
CIP
CATEGORY
PROJECT
TITLE
PROJECT
LIMITS
PROJECT
DESCRIPTION
PROJECT
BUDGET
CONSTRUCTION
SCHEDULE

Open Location Map
STREET PROJECTS OLD RIVER SCHOOL ROAD PAVEMENT REHABILITATION PROJECT IMPERIAL HWY. TO ARNETT ST.
PROJECT INCLUDES THE REHABILITATION OF EXISTING ASPHALT CONCRETE ROADWAY; REPAIR AND REPLACEMENT OF DAMAGED CURB AND GUTTER,SIDE WALK AND INSTALLATION OF NEW CURB RAMPS; REPAIR OF POTABLE WATER INFRASTRUCTURE AND REPLACEMENT OF STRIPING WITH BIKE LANES.
$1,800,000.00 JANUARY 2019 TO MAY 2019

Open Location Map
STREET PROJECTS LAKEWOOD BLVD. IMPROVEMENTS PHASE 3C GALLATIN RD. TO TELEGRAPH RD.
PROJECT INCLUDES CONTINUATION OF IMPROVEMENTS. COORDINATION WITH CALTRANS FOR PURPOSE OF OBTAINING AN ENCROACHMENT PERMIT AND WITH AFFECTED UTILITY COMPANIES PREVIOUSLY CONSTRUCTED ALONG LAKEWOOD BLVD, TO THE SOUTH, STREET WIDENING, MEDIAN AND PARKWAY IMPROVEMENTS, INCLUDING REPLACEMENT OF LANDSCAPING WITH DROUGHT-TOLERANT PLANT MATERIAL AND RECYCLED WATER IRRIGATION, ORNAMENTAL PEDESTRIAN AND STREET LIGHTING, PAVEMENT REHABILITATION, EXTENSION OF RECYCLED WATER LINE AND MISCELLANEOUS CONCRETE IMPROVEMENTS, TRAFFIC SIGNAL, SIGNAGE AND STRIPING MODIFICATIONS AND REPLACEMENT AND "GREEN STREET" ENHANCEMENTS TO FACILITATE STORMWATER INFILTRATION AND GROUNDWATER REPLENISHMENT.
$5,000,000.00 JUNE 2018 TO OCTOBER 2018

Open Location Map
STREET PROJECTS FLORENCE AVENUE BRIDGE REHABILITATON AT RIO HONDO RIVER FLORENCE AVENUE BRIDGE OVER THE RIO HONDO RIVER
THE PROJECT CONSISTS OF THE REHABILITATION OF THE FLORENCE AVENUE BRIDGE OVER THE RIO HONDO RIVER.
$2,200,000.00 APRIL 2019 TO NOVEMBER 2019

Open Location Map
STREET PROJECTS PAVEMENT REHABILITATION AT VARIOUS LOCATIONS CIVIC CENTER DRIVE, GLENCLIFF DRIVE, RIVERGROVE DRIVE, FOSTER BRIDGE BOULEVARD AND BLUFF ROAD
THE PROJECT CONSISTS OF THE REHABILITATION OF THE EXISTING ASPHALT CONCRETE ROADWAY; REPAIR AND REPLACEMENT OF DAMAGED CURB AND GUTTER AND SIDE WALK, THE INSTALLATION OF NEW CURB RAMPS AND POTABLE WATER IMPROVEMENTS.
$426,670.00 DECEMBER 2018 TO JANUARY 2019

Open Location Map
STREET PROJECTS WOODRUFF AVENUE PAVEMENT REHABILITATION IMPERIAL HIGHWAY TO STEWART AND GRAY ROAD
THE PROJECT CONSISTS OF THE REHABILITATION OF THE EXISTING ASPHALT CONCRETE ROADWAY; REPAIR AND REPLACEMENT OF DAMAGED CURB AND GUTTER AND SIDE WALK, THE INSTALLATION OF NEW CURB RAMPS AND POTABLE WATER IMPROVEMENTS.
$1,130,000.00 JANUARY 2020 TO JUNE 2020

Open Location Map
STREET PROJECTS SUVA STREET BRIDGE REHABILITATION AT THE RIO HONDO RIVER SUVA STREET BRIDGE OVER THE RIO HONDO RIVER
THE PROJECT CONSISTS OF THE REHABILITAION OF THE SUVA STREET BRIDGE OVER THE RIO HONDO RIVER. (LOS ANGELES COUNTY PROJECT)
$26,000.00 MARCH 2019 TO AUGUST 2019

Open Location Map
STREET PROJECTS BELLFLOWER BOULEVARD PAVEMENT REHABILITATION BELLFLOWER BOULEVARD, FROM IMPERIAL HIGHWAY TO STEWART AND GRAY ROAD
REHABILITATION OF EXISTING PAVEMENT; MISCELLANEOUS REPAIR OF EXISTING CONCRETE SURFACES; AND INCIDENTAL REPLACEMENT OF STRIPING AND PAVEMENT MARKINGS.
$120,000.00 AUGUST 2019 TO NOVEMBER 2019

Open Location Map
STREET PROJECTS I-5 FREEWAY (SEGMENT 5) WIDENING PROJECT I-5 FREEWAY FROM NORWALK CITY LIMIT TO FLORENCE AVENUE
THE FINAL PHASE OF THE I-5 FREEWAY WIDENING PROJECT BETWEEN THE SR 91 AND THE I-605 FREEWAYS, OTHERWISE KNOWN AS SEGMENT 5, WHICH INCLUDES THE PORTION OF THE FREEWAY BETWEEN THE NORWALK CITY BOUNDARY AND FLORENCE AVE. BUT THE WORK WILL ACTUALLY EXTEND NORTH OF THE I-605 FREEWAY IN ORDER TO PROPERLY TRANSITION WITH THE EXISTING TRAVEL LANES. THE PROJECT INVOLVES THE WIDENING OF THE I-5 FREEWAY FROM 8 TO 10 LANES AND THE REPLACEMENT OF THE FLORENCE AVE. OVERCROSSING WITH A NEW BRIDGE. IN ADDITION, FLORENCE AVE. WILL BE RECONSTRUCTED BETWEEN STUDEBAKER RD. AND ORR AND DAY RD. THE OVERALL PROJECT DURATION IS APPROX. 30 MONTHS. PLEASE BE ADVISED THAT FLORENCE AVE. WILL REMAIN DOWN TO 1 TO 2 LANES PER DIRECTION FOR APPROX. 24 MONTHS. MOTORISTS ARE ENCOURAGED TO SEEK ALTERNATE ROUTES. CALTRANS HAS DESIGNATED FIRESTONE BLVD. AS THE EASTBOUND DETOUR ROUTE AND TELEGRAPH RD. AND SLAUSON AVE. AS THE WESTBOUND DETOUR ROUTES. PLEASE CALL THE I-5 PROJECT HOTLINE AT (855) 454-6335 FOR MORE INFO.
$20,000.00 MARCH 2017 TO FEBRUARY 2020

Open Location Map
STREET PROJECTS TELEGRAPH RD. TRAFFIC THROUGHPUT AND SAFETY ENHANCEMENTS WEST CITY LIMIT TO LAKEWOOD BLVD. & PASSONS BLVD. TO EAST CITY LIMIT
PROJECT INCLUDES INSTALLATION OF RAISED MEDIAN ISLANDS WITH DROUGHT-TOLERANT LANDSCAPING AND IRRIGATION; PAVEMENT REHABILITATION; MISCELLANEOUS CONCRETE REPAIRS; ADJUSTMENTS OF UTILITY AND SURVEY COVERS TO GRADE; POTABLE WATER IMPROVEMENTS; AND REPLACEMENT OF STRIPING AND PAVEMENT MARKINGS
$8,740,000.00 AUGUST 2019 TO JANUARY 2020

Open Location Map
STREET PROJECTS FY 17/18 ANNUAL MISCELLANEOUS CONCRETE CONSTRUCTION AND REPAIR PROJECT, COUNCIL DISTRICTS 1 & 3 COUNCIL DISTRICTS 1 & 3
PROJECT CONSISTS OF MISCELLANEOUS CONCRETE CONSTRUCTION AND REPAIRS FOR PROJECT AREA. PROJECT INCLUDES REMOVAL AND RECONSTRUCTION OF PCC CURB, GUTTER, SIDEWALK, DRIVEWAYS, AND CURB RAMPS; CONSTRUCTION OF PCC SIDEWALK; REMOVAL AND RECONSTRUCTION OF AC PAVEOUTS; CLEARING, GRADING, EXCAVATION, AND TREE ROOT REMOVALS; BACKFILLING, RE-GRADING, RESTORATION OF PARKWAYS AND AREAS DISTURBED BY THE CONSTRUCTION; RESEEDING AND/OR PLANTING SOD TURF
$300,000.00 AUGUST 2018 TO OCTOBER 2018

STREET PROJECTS FY 17/18 RESIDENTIAL STREET RESURFACING CITYWIDE
PROJECT CONSISTS OF THE PAVEMENT REHABILITATION OF THE EXISTING RESIDENTIAL STREETS CITYWIDE. PROJECT INCLUDES INSTALLATION OF ASPAHLT CONCRETE PAVEMENT OVERLAY; REPAIR AND REPLACEMENT OF DAMAGED CURB, GUTTER, SIDEWALK; INSTALLATION OF NEW CURB RAMPS; REPLACEMENT OF TRAFFIC STRIPING, PAVEMENT MARKINGS, AND RAISED PAVEMENT MARKERS.
$1,298,000.00 AUGUST 2018 TO DECEMBER 2018

Open Location Map
STREET PROJECTS TWEEDY LANE PAVEMENT REHABILITATION FLORENCE AVENUE TO SUVA STREET
PROJECT INCLUDES THE REHABILITATION OF EXISTING ASPHALT CONCRETE ROADWAY; REPAIR AND REPLACEMENT OF DAMAGED CURB AND GUTTER, SIDEWALK; INSTALLATION OF NEW CURB RAMPS; REPLACEMENT OF TRAFFIC STRIPING, PAVEMENT MARKINGS, AND RAISED PAVEMENT MARKERS.
$370,000.00 JANUARY 2019 TO MARCH 2019

STREET PROJECTS FIRESTONE BLVD. PAVEMENT REHABILITATION DOWNEY AVENUE TO MYRTLE STREET
PROJECT CONSISTS OF THE REPAIR OF THE EXISTING ASPHALT PAVEMENT ON WESTBOUND FIRESTONE BOULEVARD
$450,000.00 JANUARY 2019 TO MARCH 2019

STREET PROJECTS FY 18-19 PEDESTRIAN IMP/NEW SIDEWALK /RAMP CONSTRUCTION (DISTRICT 2) & ADA IMPROVEMENTS COUNCIL DISTRICT 2
PROJECT CONSISTS OF MISCELLANEOUS CONCRETE CONSTRUCTION, REPAIRS AND ADA IMPROVEMENTS. PROJECT INCLUDES REMOVAL AND RECONSTRUCTION OF PCC CURB, GUTTER, SIDEWALK, DRIVEWAYS, AND CURB RAMPS; CONSTRUCTION OF PCC SIDEWALK; REMOVAL AND RECONSTRUCTION OF AC PAVEOUTS; CLEARING, GRADING, EXCAVATION, AND TREE ROOT REMOVALS; BACKFILLING, RE-GRADING, RESTORATION OF PARKWAYS AND AREAS DISTURBED BY THE CONSTRUCTION; RESEEDING AND/OR PLANTING SOD TURF
$457,781.00 JANUARY 2019 TO MARCH 2019

STREET PROJECTS FY 18-19 ANNUAL SLURRY SEAL PROGRAM (INCLUDES ARTERIALS) (DISTRICT 3) COUNCIL DISTRICT 3
PROJECT INCLUDES SEALING CRACKS IN THE ASPHALT PAVEMENT, APPLYING A TYPE II SLURRY SEAL COAT TO THE PAVEMENT SURFACE, REPLACEMENT OF TRAFFIC STRIPING, PAVEMENT MARKINGS, AND RAISED PAVEMENT MARKERS
$300,000.00 MARCH 2019 TO APRIL 2019

STREET PROJECTS FY 18-19 RESIDENTIAL STREET PAVEMENT REHABILITATION CITYWIDE
PROJECT CONSISTS OF THE PAVEMENT REHABILITATION OF THE EXISTING RESIDENTIAL STREETS CITYWIDE. PROJECT INCLUDES INSTALLATION OF ASPAHLT CONCRETE PAVEMENT OVERLAY; REPAIR AND REPLACEMENT OF DAMAGED CURB, GUTTER, SIDEWALK; INSTALLATION OF NEW CURB RAMPS; REPLACEMENT OF TRAFFIC STRIPING, PAVEMENT MARKINGS, AND RAISED PAVEMENT MARKERS
$2,617,000.00 MARCH 2019 TO JUNE 2019

Open Location Map
TRAFFIC PROJECTS PARAMOUNT BOULEVARD MEDIAN ISLAND PROJECT IMPERIAL HIGHWAY TO FIRESTONE BOULEVARD
PROJECT INCLUDES THE INSTALLATION OF MEDIANS ON PARAMOUNT BOULEVARD FROM IMPERIAL HIGHWAY TO FIRESTONE BOULEVARD WITH DROUGHT-TOLERANT LANDSCAPING AND NEW IRRIGATION
$1,710,000.00 DECEMBER 2018 TO APRIL 2019

Open Location Map
TRAFFIC PROJECTS PARAMOUNT BOULEVARD MEDIAN ISLAND PROJECT FIRESTONE BOULEVARD TO FLORENCE AVENUE
PROJECT INCLUDES THE CONSTRUCTION OF MEDIAN ISLANDS ON PARAMOUNT BOULEVARD BETWEEN FIRESTONE BOULEVARD AND FLORENCE AVENUE WITH DROUGHT-TOLERANT LANDSCAPING AND NEW IRRIGATION AND PAVEMENT REHABILITATION BETWEEN FLORENCE AVENUE AND 7TH STREET.
$1,739,000.00 MAY 2019 TO SEPTEMBER 2019

TRAFFIC PROJECTS FIRESTONE BOULEVARD MEDIAN PROJECT (OLD RIVER SCHOOL ROAD TO THE WEST CITY LIMIT) FIRESTONE BOULEVARD, FROM OLD RIVER SCHOOL ROAD TO THE WEST CITY LIMIT
PROJECT INCLUDES CONSTRUCTION OF RAISED MEDIAN ISLAND WITH LANDSCAPING AND IRRIGATION.
$1,439,720.00 JANUARY 2019 TO MAY 2019

Open Location Map
TRAFFIC PROJECTS WOODRUFF AVENUE FIBEROPTIC COMMUNICATIONS & TRAFFIC SIGNAL UPGRADES PROJECT FOSTER ROAD TO FIRESTONE BOULEVARD
PROJECT INCLUDES INSTALLATION OF FIBER OPTIC CONDUIT, CABLES AND COMMUNICATION DEVICES ALONG WOODRUFF AVENUE FROM THE FOSTER ROAD TO FIRESTONE BOULEVARD. ALSO INCLUDES CONNECTIONS TO TRAFFIC SIGNAL CONTROLLER CABINETS TO ALLOW FOR REMOTE TRAFFIC SIGNAL SURVEILLANCE AND OPERATION FROM THE TRAFFIC MANAGEMENT CENTER IN CITY HALL AND TRAFFIC SIGNAL UPGRADES AT VARIOUS INTERSECTIONS ALONG WOODRUFF AVENUE.
$854,164.00 JANUARY 2019 TO JUNE 2019